Lucerne Pavilion Hospital

Location

Orlando Florida

Scope of Work

Complete demolition of a 5 story 350,000 square foot hospital located in the heart or down town Orlando. Our scope also included complete asbestos abatement of floor tile and duct mastic. All of the concrete generated from this project was recycled onsite and used as road base for other local projects.

Customer

Orlando Health

Read more

Project 942

Location

Universal Studios Orlando

Scope of Work

Complete demolition of the largest steel rollercoaster in Orlando and all systems located in the ride envelope. The steel coaster was 120′ tall and the total track length of 6,500′ was demolished in only 3 weeks. The coaster was 100% recycled including 100,000 pounds of stone ballast located inside the track element was re-puposed inside the the project. There where 150 concrete foundations demolished and crushed into 15,000 tons of recycled concrete. 50% of the foundations were 20′ deep into the ground and required a project specific dewatering plan to efficently remove them.
P942-Progess-min.pdf

Customer

Universal Studios Orlando

Read more

Washington Shores

Location

Orlando Florida

Scope of Work

Complete demolition of an entire public housing community. Total square footage of all the buildings was 300,000 square feet. Our asbestos abatement crews removed over 1,100,000 suare feet of friable and regulated coating on the walls of the housing units prior to starting the demolition.

Customer

Columbia Residential

Read more

Freedom Plaza

Location

Washington DC

Scope of Work

Complete demolition of a 12 story office building 2 blocks from the White House. The building was 200,000 square footage and surrounded by 3 story buildings that were inches way and could not get damaged. Our team successfully developed a plan and system that allowed us to use our high reach excavator without damaging any of the adjacent buildings or the parking garage located underneath the building we demolished.

Customer

Hensel Phelps Construction

Read more

Disney Springs

Location

Walt Disney World

Scope of Work

Complete demolition of 20 buildings located in former “Down Town Disney” area to make way for the new “Disney Springs” entertainment district. The scope covered over 300,000 square feet of building demolition in areas immedialtry adjacent to active guest areas. Our team successfully demolished the Captain Jack’s Restuarant which was originally built over the water and could only be accessed via a barge on the water.

Customer

PCL Construction

Read more

Orbiter Processing Facilities

Location

Kennedy Space Center Florida

Scope of Work

Complete demolition of all 3 space shuttle hangers that were 90′ tall and covered a total of 150,000 square feet. This was a very complex project since the main hanger super structure which was only inches away from the Orbiter Support Structures could not get damaged. We developed a unique system to protect all of the historic systems and components before starting the demolition and successfully removed over 4,000 tons of steel without any damage to the items remaining.

Customer

Hensel Phelps Construction

Read more

Disney Hollywood Studios

Location

Orlando Florida

Scope of Work

Complete demolition of almost 1/3 of this historic theme park. The scope covered approximately 25 buildings totaling 600,000 square feet of building space, the 10 story tall “Lights, Motors & Action” Stadium and the original “Catastrphe Canyon” ride. We recycled 95% of the demolition waste and removed the “Earful” water tower in a 6 hour shift in the middle of the night to not impact the guest experiance.

Customer

Hubbard Construction

Read more

Tyco Electronics Demolition

Location

Melbourne, Fl

Scope of Work

Hazardous waste removal and demolition and removal of 50,000 SF building and waste water treatment plant. This Tyco facility manufactured printed circuit boards for over 30 years. Every inch of the facility was cleaned of RCRA-8 hazardous metals residue prior to demolition.

Customer

Shaw Environmental Inc

Read more

Delta Hotel Abatement & Demolition

Location

Orlando, Fl

Scope of Work

Complete demolition of the former Delta Resort in Orlando, FL Consisting of over 450,000 square feet of buildings, 3 large swimming pools and a miniature golf course. Four of the buildings were four stories in height and required the use of our Ultra High excavator to safely and efficiently demolish the buildings while allowing for the most effective way to recycle the steel frame structures.

Customer

Hensel Phelps

Read more

Evans High School Demolition

Location

Orlando, Fl

Scope of Work

Demolition and removal of 320,000 SF school located in Orange county Florida. This project consisted of complete demolition of 22 buildings including the 95 foot tall auditorium building. Due to an aggressive build back schedule all demolition had to be completed in 8 weeks therefore Pece Of Mind completed all of the demolition in 7 Weeks!

Customer

Williams Company

Read more