University Of Florida Stephen O’Connell Stadium

Location:

Gainesville FL

Scope of Work:

Complete interior structural demolition of the stadium to make way for the new club-level suites and concession areas. The total of work areas was 350,000 square feet. Due to an extremely tight schedule we designed a critical lift and rigging plan to bring a large crane inside the stadium to efficently remove the large precast concrete sections, saving the client weeks on the schedule.

Completion Date:

October 2017

Customer:

Brasfield & Gorie Construction